Question: ( Please Round your answers to nearest integer number ) Question. 2: The schedule baseline of a small construction Project. According to the field progress

Question. 2: The schedule baseline of a small construction Project. According to the field progress report the position of the activities at the end of the 26th day is as follows: -Activities A, B, C, and have been completed. - Remaining durations of activities E, F, G, and H are 10, 9, 5. and 10 days, respectively. -Activity G will not start until end of day 25 -Volume of work in activity J has been increased by 33% approximately. - Activity L has been cancelled. Durations (Days) Activity B C D E F G H Predecessors None A A B C D D E and F F and G H Tand Kand MandN 11 15 8 11 18 8 11 15 12 8 11 13 12 11 K L M N Compute the ES and EF of the following activities Activity ES EF E F G HT I J K M N