Question: PLEASE SEND ANSWER AS SOON AS POSSIBLE!!!! 2. Given the project information below, what is the probability of completing the National Holiday Toy project in

PLEASE SEND ANSWER AS SOON AS POSSIBLE!!!!
2. Given the project information below, what is the probability of completing the National Holiday Toy project in 100 time units? (5 points) None 1 1 2 3 4 5 Act. ID Description Predecessor Optm. (a) Most likely (m) Pess. (b) Act time t, Variance [(b-a)/6]2 Critical Design package Design product Build package 1 Secure patent Build product 6 Paint 3,4,5 Test market 7 18 3 21 14 7 16 2 2 13 21 5 29 26 9 20 25 30 10 40 44 13 7 6 24Step by Step Solution