Question: PLEASE SHOW ALL CALCULATIONS PLEASE SHOW ALL CALCUALTIONS E18-12B (Recognition of Profit on Long-Term Contracts) During 2014 AFCO started a construction job with a contract

PLEASE SHOW ALL CALCULATIONS PLEASE SHOW ALL CALCUALTIONS

E18-12B (Recognition of Profit on Long-Term Contracts) During 2014 AFCO started a construction job

with a contract price of $2,500,000. The job was completed in 2016. The following information is available.

2014 2015 2016

Costs incurred to date $ 600,000 $1,435,000 $2,100,000

Estimated costs to complete 1,400,000 615,000 0

Billings to date 100,000 500,000 2,500,000

Collections to date 100,000 300,000 2,000,000

Instructions

(a) Compute the amount of gross profit to be recognized each year assuming the percentage-ofcompletion

method is used. PLEASE SHOW CALCULATIONS

(b) Prepare all necessary journal entries for 2015. PLEASE SHOW CALCUALTIONS

(c) Compute the amount of gross profit to be recognized each year assuming the completed-contract

method is used. PLEASE SHOW CALCULATIONS

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!