Question: please show all work! 3. A project manager has compiled a list of major activities that will be required to install a computer information system
please show all work!
3. A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes the precedence relationships and estimated completion time for each activity. Please compute the expected time and standard deviation for each path. What is the probability that this project will finish within 25 weeks? Activity AB A CPE D F GH End B - Immediate Predecessor A B AC E D, E F G, H D G 6-9-10 6-8-10 4-5-6 4-5-7 7-9-11 4-5-8 6-8-18 5-6-9 H Time in weeks (Optimistic-Most likely-Pessimistic)