4. Based on precedence diagram given below, use the longest task time heuristic to balance the line. Cycle time =1.3 minute Task and time (min.) A,0.2 B, 0.4 C, 0.3 D, 1.3 E, 0.1 F, 0.8 G, 0.3 H, 1.2 What is the balance delay? Out of all workers placed which worker is the happiest (has most remaining time)