Question: **** Please show all work and provide a complete explanation**** A B ... 15.23 Six jobs are to be processed through a two-step opera- tion.

**** Please show all work and provide a complete explanation****

**** Please show all work and provide a complete

A B ... 15.23 Six jobs are to be processed through a two-step opera- tion. The first operation involves sanding, and the second involves painting. Processing times are as follows: JOB OPERATION 1 (HOURS) OPERATION 2 (HOURS) 10 5 B 4 C 5 7 D E 6 F 3 3 Determine a sequence that will minimize the total completion time for these jobs. Illustrate graphically. PX 4 7 8 D NWU AN F 4