Question: please show all work and use excel A re Help Center? Use the following information for a project: Activity Immediate Activity Time Predecessor (days) A

please show all work and use excel
please show all work and use excel A re Help
A re Help Center? Use the following information for a project: Activity Immediate Activity Time Predecessor (days) A 3 B A C A 5 D B,C E C F D,E 3 Below, you will need to perform four tasks: (a) create Gantt Chart of the project; (b) draw the AOA (Activity-On-Arrow) project network; (c) Formulate LP problem, that is, write down objective function and constraints: (d) solve the problem in Excel