Question: Please show all work, calculation, or explanation to receive full credit and circle the correct answer. Use the following Information to Answer Problems 1 and
- Please show all work, calculation, or explanation to receive full credit and circle the correct answer.
Use the following Information to Answer Problems 1 and 2
| Bradford Services Inc. (BSI) is considering a project that has a cost of $10 million and an expected life of 3 years. There is a 30 percent probability of good conditions, in which case the project will provide a cash flow of $9 million at the end of each year for 3 years. There is a 40 percent probability of medium conditions, in which case the annual cash flows will be $4 million, and there is a 30 percent probability of bad conditions and a cash flow of -$1 million per year. BSI uses a 12 percent cost of capital to evaluate projects like this. | |
Problem 1: Find the projects expected cashflow and NPV
| Condition | Probability | Cash Flow | Prob.*Cash Flow |
| Good | 0.3 | $9 |
|
| Medium | 0.4 | $4 |
|
| Bad | 0.3 | -$1 |
|
|
|
| Expected CF |
|
| Expected CF =
|
|
| T=0 | T=1 | T=2 | T=3 |
| CF |
|
|
|
|
| NPV of Project =
|
| What can you conclude regarding this project?
|
Problem 2: find the projects standard deviation and coefficient variation?
| Condition | Probability | NPV |
| Good | 0.3 |
|
| Medium | 0.4 |
|
| Bad | 0.3 |
|
|
| Expected NPV |
|
NPV of Project in Good Condition =
NPV of Project in Average Condition =
NPV of Project in Bad Condition =
| Variance =
|
| Coefficient Variation =
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
