Question: Please show all work in Excel and explain steps A snowmobile manufacturer produces three models, the XJ6, the XJ7, and the XJ8. In any given
Please show all work in Excel and explain steps

A snowmobile manufacturer produces three models, the XJ6, the XJ7, and the XJ8. In any given production planning week, the company has 40 hours available in its final testing bay. Each XJ6 requires 1 hour of testing, each XJ7 requires 1.5 hours, and each XJ8 takes 1.6 hours. The revenue (in \$thousands) per unit of each model is defined as ($4$0.1X1) for XJ6, ($5$0.2X2) for XJ7, and ($6$0.2X3) for XJ8, where X1,X2, and X3, and are the numbers of XJ6,XJ7, and XJ8 models made, respectively. Formulate this problem to maximize revenue and solve it by using Excel
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts