Question: Please show all work, step-by-step. Another user answered the same question, however, they did not provide enough work shown. Question 6 (45 points). Consider the

Please show all work, step-by-step. Another user answered the same question, however, they did not provide enough work shown.
Question 6 (45 points). Consider the following data for a project to install a new server at the Northland Pines High School: Activity Activity Time (days) Immediate Predecessor(s) A B, C DE F | G, HI J7 a) Draw the network diagram. b) Calculate the critical path for this project. c) How much slack is in each activityStep by Step Solution