Question: Please show all your work for each sub question. No credit will be assigned if no work is shown. On For the following precedence relationship,


Please show all your work for each sub question. No credit will be assigned if no work is shown. On For the following precedence relationship, answer questions Precedence Activity A D E F G H A A B,C CD D Estimated Time (Weeks) 10 10 5 20 15 15 10 15 10 20 E,F 1 F,G HI The total duration for the project is: a. 30 weeks b. 25 weeks C. 43 weeks d 80 weeks The Critical path for the above project is: a. A-C-F-H- b. A-C-F-H-J and A-C-F-I-J C. A-D-F-H- d. A-D-G-H- The slack associated with activity Fis: a. 3 weeks b4weeks C. 7 weeks dO weeks. The slack associated with activity I is which of the following: a 5 weeks b. 2 weeks C. O weeks d. 3 weeks. The slack associated with activity G is: a. O weeks b. 10 weeks C. 5 weeks d. 1 week. The slack associated with activity E is: a. 4 weeks b. 2 weeks 10 weeks d. 0 weeks. The slack associated with activity Cis which of the following: a. 15 weeks b. 10 weeks C. 20 weeks d. 5 weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
