Question: PLEASE SHOW EXCEL FORMULA & STEPS TO SOLVE PROBLEM Given the information in the table below, calculate the NPV and IRR for projects A and

PLEASE SHOW EXCEL FORMULA & STEPS TO SOLVE PROBLEM

Given the information in the table below, calculate the NPV and IRR for projects A and B. Assuming these are mutually exclusive projects, which project should the firm choose?
Project A Project B
Year Cash Flow Cash Flow
0 ($105.00) ($70.00)
1 $55.00 $30.00
2 $45.00 $30.00
3 $35.00 $30.00
4 $25.00 $30.00
Discount Rate 13.50% 14.50%
Use the scratchpad to show your work in Excel.
Type your numercial answers into the yellow cells below.
Answers should be to two decimal places, e.g. 1.23% or $123.45.
NPV A
IRR A
NPV B
IRR B
Choose A or B?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!