Question: PLEASE SHOW EXCEL SOLUTION WITH STEPS> THANK YOU A construction company only makes one home type, so as to maximize the learning curve effect. The

PLEASE SHOW EXCEL SOLUTION WITH STEPS> THANK YOUPLEASE SHOW EXCEL SOLUTION WITH STEPS> THANK YOU

A construction company only makes one home type, so as to maximize the learning curve effect. The manager assumes that they will realize a 80% learning curve effect. If the first home took 200 days to complete: 1. How long will it take to complete the 5th home (1point)? 2. How long will it take to complete the first 5 homes (1point)? Please show the calculation otherwise you cannot get any score. You can do the calculation on a sheet of paper, and then paste it in this sheet