Question: Please show how to come to answer. This question confused me The predetermined overhead rate for manufacturing overhead for 2012 is $5 00 per direct
Please show how to come to answer. This question confused me
The predetermined overhead rate for manufacturing overhead for 2012 is $5 00 per direct labor hour. Employees are expected to earn $6 00 per hour and the company is planning on paying Its employees $68,000 during the year However, only 75% of the employees are classified as "direct labor." What was the estimated manufacturing overhead for 2012? $42,500. $51,000. $56,667. $64,600