Question: Please show how to come to answer. This question confused me The predetermined overhead rate for manufacturing overhead for 2012 is $5 00 per direct

Please show how to come to answer. This question confused me Please show how to come to answer. This question confused me The

The predetermined overhead rate for manufacturing overhead for 2012 is $5 00 per direct labor hour. Employees are expected to earn $6 00 per hour and the company is planning on paying Its employees $68,000 during the year However, only 75% of the employees are classified as "direct labor." What was the estimated manufacturing overhead for 2012? $42,500. $51,000. $56,667. $64,600