Question: PLEASE SHOW HOW YOU GOT EACH ANSWER STEP BY STEP A billiard ball maker must place orders for resin, a raw material for billiard balls.
PLEASE SHOW HOW YOU GOT EACH ANSWER STEP BY STEP
A billiard ball maker must place orders for resin, a raw material for billiard balls. It uses resin at a rate of 120 kilograms each day, and incurs a cost of $0.4 per kilogram per day to hold inventory. The ordering cost is $150 per order. Lead time for delivery is 4 days. Assume 365 day in a year. What is the optimal length of the order cycle associated with the minimum total cost of ordering and inventory holding? [Round your final number with two decimals] 0.13 days 1.10 days 2.50 days 47.76 days None of the above
Step by Step Solution
There are 3 Steps involved in it