Question: Please show how you got the answers! 4. Develop a lot-for-lot solution of component X for the given gross requirements. It is the beginning of

Please show how you got the answers!

Please show how you got the answers! 4. Develop a

4. Develop a lot-for-lot solution of component X for the given gross requirements. It is the beginning of week 1 and there are currently 30 units of component X in stock. Component X has a lead time of 2 week. There are scheduled receipts planned for week 3 and week 4 of 20 each. Week 1 2 3 4 5 100 500 oss requirements (start of period) Schedule receipts (start of period) Projected on hand (start of period) Net requirements Planned order receipts Planned order releases the onerations