Question: PLEASE SHOW IN EXCEL: A. Determine the expected duration and variance for each activity. B. Determine the ES, EF, LS, LF, and slack time for

PLEASE SHOW IN EXCEL:

A. Determine the expected duration and variance for each activity.

B. Determine the ES, EF, LS, LF, and slack time for each activity. Also determine the total project completion time and critical path(s).

C. What is the probability that this job will finish in 38 days or less?

PLEASE SHOW IN EXCEL: A. Determine the expected

11-18 The Laurenster Corporation is getting into the construction business. A list of activities and their optimistic, most likely, and pessimistic completion times are given in the following table for the next construction project ACTIVITY DAYS IMMEDIATE PREDECESSORS a m b A 3 6 - B 2 4 6 - 1 2 3 D 6 07 7 8 00 E 2 4 6 B, D F 6 10 14 A, E G G 1 2 09 A, E H H 3 6 9 F 10 11 12 J 14 16 21 G K N 8 8 11 HI

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!