Question: Please show work. Practice: Problem 4 Solue for Unknown 4 The direct labor standard indicates two direct labor hours should be used for one unit
Please show work.
Practice: Problem 4 Solue for Unknown 4 The direct labor standard indicates two direct labor hours should be used for one unit of product. The standard rate for VOH is $3 per DLH. During the quarter, the direct labor hours used were 10% less than expected. VOH efficiency variance = $300 F LEV = $150 F LRV = $90 u Required: Determine (1) the actual direct labor hours; (2) the total hours allowed; (3) the standard hourly rate; (4) the actual hourly rate; (5) the actual units produced