Question: Please show work Problem 1 (5 points): Please read the following Table, which has 6 weeks. The opening inventory is 20. As master scheduler, you

Please show work
Problem 1 (5 points): Please read the following Table, which has 6 weeks. The opening inventory is 20. As master scheduler, you must prepare an MPS. The lot size is 100. Complete the projected available balance and the master production schedule. Please fill in all of the blanks in the following Table. a 1 10 2 50 3 25 4 50 5 20 6 15 Week Forecast Sales Projected 20 Available Balance MPSStep by Step Solution