Question: Please show work! Task Duration (days) AC after 15 days % complete AC after 20 after 20 days days 100 A B 10 100 100

Please show work!
Task Duration (days) AC after 15 days % complete AC after 20 after 20 days days 100 A B 10 100 100 TIT D Predecessors Budget % complete after 15 days $2560 100 2800 100 A 1920 100 A 3240 95 B 1730 20 C 3280 10 C D 3648 5 E, F 1280 0 G 870 0 HI 320 0 1598961431 2600 2750 2000 3000 450 450 350 E 2600 2750 2000 3000 1450 2100 1400 100 75 60 40 F G 10 12 . 0 0 0 0 0 0 1 J 0 0 0 a. b. (3 pts) Calculate EV and PV for each task and the total for the project for each time period. (3 pts) Calculate the CV, SV, CPI and SPI, ETC and EAC for the project (don't need each task) at each of those time periods. (1 pt) What can you say about the health of the project? cStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!