Question: please show work The project has a total budgeted amount of $200,000 and is scheduled to take 12 months. At the end of the third

please show work please show work The project has a total budgeted
The project has a total budgeted amount of $200,000 and is scheduled to take 12 months. At the end of the third month the EV = $50,000 and a SP1 of 1.1 and CPI of 1.2. What is the AC? What is the PV? What is the EAC? What does this mean? What is the estimated time to completion? What does this mean? Briefly discuss the output. Are you over/under budget? Are you ahead/behind schedule