Question: please show your work explaining how many days it took to complete the project. 14. Using the basic chart below develop a Gantt chart showing
14. Using the basic chart below develop a Gantt chart showing the tasks, elapsed time, and completion day for the following project: to build a two car brick garage. A=15daysB=10daysC=5daysD=3daysE=7daysF=10daysG=5daysPrecedenceNonePrecedenceNonePrecedenceAPrecedenceBPrecedenceDPrecedenceEPrecedenceF