Question: please solve. (21 points) Os 2. The following data for the Arm & Cost Grenade company apply to the production of 2000 grenades last month.

please solve. (21 points) Os 2. The following data for the Armplease solve.

(21 points) Os 2. The following data for the Arm & Cost Grenade company apply to the production of 2000 grenades last month. Direct Materials (all materials purchased were used) Standard Cost: Total Actual Cost; Standard Cost Allowed for Grenades produced Materials efficiency variance Rs 60 per pound of explosive Rs 112,000 Rs 120,000 Rs 2400 (Unfavorable) What was the Direct Materials Price variance? (12 pts)