Question: please solve and fill in the table? The demand for subassembly S is 150 units in week 7 . Each unit of S requires 1

The demand for subassembly S is 150 units in week 7 . Each unit of S requires 1 unit of T and 1 unit of U. Each unit of Trequires 1 unit of V,2 units of W, and 1 unit of X. Finalify, each unit of U weeks to make Y, and 2 weeks to make Z. Click the icon to vew the product structure and the time-phased product structure. Click the icon to view the product structure and the time-phased product structure. Construct a gross material requirements plan ( 0 po 0 if tho input box is not used)