Question: please solve and show the chart and es ls ef lt 3 . Cypress accounting firm has been hired to perform an audit. The audit
please solve and show the chart and es ls ef lt Cypress accounting firm has been hired to perform an audit. The audit has been divided into nine activities. The firm has estimated the optimistic a pessimistic b and most likely m times for each task as shown in the table below.
Task Times weeks
Task Predecessors a m b please add the es ef ls lf for each letter
A None
B None
C None
D A B
E A B C
F D E
G F
H F
I G H
a Construct a network diagram for the project.
b Compute the expected completion time for the project.
c Compute the probability that the audit will take more than weeks to complete.