Question: please solve and show the chart and es ls ef lt 3 . Cypress accounting firm has been hired to perform an audit. The audit

please solve and show the chart and es ls ef lt3. Cypress accounting firm has been hired to perform an audit. The audit has been divided into nine activities. The firm has estimated the optimistic (a), pessimistic (b), and most likely (m) times for each task as shown in the table below.
Task Times (weeks)
Task Predecessors a m b please add the es ef ls lf for each letter
A None 4610
B None 235
C None 125
D A, B 236
E A, B, C 4712
F D, E 124
G F 247
H F 3610
I G, H 124
a. Construct a network diagram for the project.
b. Compute the expected completion time for the project.
c. Compute the probability that the audit will take more than 26 weeks to complete.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!