Question: Please solve. Current Attempt in Progress Cullumber Company has the following production data for March: no beginning work in process, units started and completed 27,500,
Please solve.

Current Attempt in Progress Cullumber Company has the following production data for March: no beginning work in process, units started and completed 27,500, and ending work in process 5,300 units that are 100% complete for materials and 40% complete for conversion costs. Cullumber uses the FIFO method to compute equivalent units. If unit materials cost is $5 and unit conversion cost is $14, determine the costs to be assigned to the units transferred out and the units in ending work in process. The total costs to be assigned are $578,680. Transferred out $ Ending work in process