Question: please solve fast please b) Dekmal Beauty Sdn. Bhd. has four Project Engineers to be assigned to three projects. Find the assignment of Project Engineer
please solve fast please
b) Dekmal Beauty Sdn. Bhd. has four Project Engineers to be assigned to three projects. Find the assignment of Project Engineer to project that will minimize the total time to complete all projects. The estimated project completion times in days are as in Table Q3(b). Table Q3() Project Engineer "Atiah Choong Sharifah Shimah School 9 8 5 7 Project Hospital 14 17 13 15 Bridge 8 4 2 5 i. Use the Hungarian method to obtain TWO optimal solutions. ii. What is the total completion time