Question: please solve for e only, all others are solved, E only. . As data provided in the question: - PV= $23,000 EV=$20,000 AC=$25,000 BAC=$120,000 a

please solve for e only, all others are solved, E only.

.please solve for e only, all others are solved, Eplease solve for e only, all others are solved, E

As data provided in the question: -

PV= $23,000

EV=$20,000

AC=$25,000

BAC=$120,000

a.

1. Cost Variance = EV-AC = 20,000-25,000= -$5,000

2. Schedule Variance = EV-PV = 20,000-23,000= - $3,000

3. CPI= EV/AC = 20,000/25,000 = 0.8

4. SPI = EV/PV =20,000/23,000 = 0.87

b.

1. When SPI is less than 1 then it indicates that the project is behind schedule to date. In this case SPI value is 0.87 which is less then 1, so it indicates it is behind schedule.

Also, negative schedule variance means that a project is behind schedule

2. As the cost variance is negative it implies that project is under budget.

c.

EAC = BAC/CPI = 120,000/0.8 = $150,000

Please note this is the case when we assume that this project will continue to perform to the end as it was performing until now. i.e. the CPI will remain the same for the rest of the project.

d. EAC = AC+ (BAC-EV)/(CPI*SPI)

=25,000 + (120,000-20,000)/ (0.8*0.87)

= 25,000 + (100,000/0.696)

=25,000 + 143,678

= 168,678

please solve for e, only e.

60.0% 51.3% 50.0% 40.0% 35.8% A few pilot projects 31.9% 32.2% 29.2% Percent Using EVM 30.0% Large and critical projects 19.5% 20.0% Organization-wide standard for all projects 10.0% 0.0% Defense/Government Private industry Source: Lingguang Song, Earned Value Management: A Global and Cross-Industry Perspective on Current EVM Practice, PMI (2011). Figure 8-4. Percentage of organizations using EVM Please solve, most important part e, Thank you Given the following information for a one-year project, answer the following questions. Assume you have actual and earned value data at the end of the second month. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $23,000, EV = $20,000, AC = $25,000, BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project progressing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? c. Use the CPI to calculate the estimate at completion (EAC) for this project. d. Use the SPI to estimate how long it will take to finish this project. e. Sketch the earned value chart for this project, using Figure 8-4 as a guide. Assume the data for month 1 is half of the values given for PV, EV, and AC at the end of month 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!