Question: Please solve it as soon as possible Question 7 10 pts The following activities constitute the critical path of a project. The table below gives
Please solve it as soon as possible
Question 7 10 pts The following activities constitute the critical path of a project. The table below gives details on the time estimates for completion of each task. Activity Optimistic Most Likely Pessimistic Predecessor A 2 5 8 B 4 10 22 A 1 4 16 B D 4 6 00 What is the expected duration of this project? (Enter your answer as a number only, do not include units or any other text. If appropriate, decimal points are ok, but no other punctuation, etc.)