estion 21 In MRP, planned order receipts must always equal: covered larked out of 00 Select one: a. planned order releases b. scheduled receipts C. gross requirements d. net requirements P Flag cuestion on 22 Two units of sub-component Z go into each unit of component Q, and Z doesn't go into anything other than Q. Z's lead time is one week. Q's lead time is two weeks. Q has a planned order release of 400 units in week 5. As regards Z, therefore,gross requirements in week are 800 red dout of Select one: a question a. five b. Seven C. Six d. fourStep by Step Solution