Question: Please solve the following problems related to Chapter 17: Project Management 1. Based on the following AOA diagram, please answer the following question: (1) Determine
Please solve the following problems related to Chapter 17: Project Management 1. Based on the following AOA diagram, please answer the following question: (1) Determine the critical path and the expected project duration (2) Determine the following quantities for each activity, the earliest start time, the latest start time, the earliest finish time and the latest finish time and the slack time. I C (7) F (5) A (4) |(6) D (11) GB) H(10) B (9) E (12)