Question: please solve the question with steps QUESTION 8 You are working on a project; the following information is given; Earned value = 400 S Planned

please solve the question with steps
QUESTION 8 You are working on a project; the following information is given; Earned value = 400 S Planned Value = 500 S Actual cost = 400 $ Original Budget = 1000 $ Original Time Estimate = 20 Months Calculate following thing. (i) The project is behind schedule or ahead of the schedule? (ii) The project is under budget or over budget? (iii) What is the estimated budget at the end? (iv) What is the estimated time to end for the projectStep by Step Solution