Question: please solve the question with steps QUESTION 8 You are working on a project; the following information is given; Earned value = 400 S Planned

please solve the question with steps QUESTION 8

please solve the question with steps

QUESTION 8 You are working on a project; the following information is given; Earned value = 400 S Planned Value = 500 S Actual cost = 400 $ Original Budget = 1000 $ Original Time Estimate = 20 Months Calculate following thing. (i) The project is behind schedule or ahead of the schedule? (ii) The project is under budget or over budget? (iii) What is the estimated budget at the end? (iv) What is the estimated time to end for the project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!