Question: Please solve these questions by choosing the correct answer | The most likely estimate of site excavation duration is 5 days, the optimiste and the

Please solve these questions by choosing the correct answer
| The most likely estimate of site excavation duration is 5 days, the optimiste and the pessimistic estimate is 8 days. The weighted average duration is: A) 0.562 days B) 5.25 days C) 5.5 days D) 5 days A project's current EV is $25,000 and SV is $5,000. What is the project's current si A) 1 B) 1.25 C) 0.83 D) 0.2 A project has the following measurements: EV=100, PV=180, CPI=1, SV=80. How much is the Actual Cost? | A 100 B) 80 C) 180 D) 0 Winicii ui liese is correci with respec io a produci developeu or a service periorme: A) Bad quality is acceptable, but bad grade is | B) Bad grade is acceptable, but bad not. quality is not C) Neither bad grade nor quality is acceptable. D Grade and quality is the same thing. | B) Quality is defined as: A) The degree to which a set of inherent characteristics fulfills requirements C) The process of identifying which quality standards are relevant to the project The customer's need to be involved in the process Quality is inspected not built into a result | D)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
