Question: please solve this A project has an initial cash outlay of $16,500. Cash inflows are $5,200 in year 1,$6,700 in year 2 , and $8,100

please solve this
A project has an initial cash outlay of $16,500. Cash inflows are $5,200 in year 1,$6,700 in year 2 , and $8,100 in year 3 . What is the net present value if an 8.40% discount rate is applied to this project? Multiple Choice $305.36 $475.88 $574.76