Question: Please solve this and find the ----->>> MPS start and the Available-to-promise (ATP) inventory for each B) Four customer orders arrived in the following sequence:
Please solve this and find the ----->>> MPS start and the Available-to-promise (ATP) inventory for each
B) Four customer orders arrived in the following sequence:
| Order | Quantity | Week Desired |
| 1 | 600600 | 4 |
| 2 | 300300 | 5 |
| 3 | 200200 | 1 |
| 4 | 200200 | 77 |
Assume that you commit to the orders in the sequence of arrival and cannot change the desired shipping dates or your MPS. Which orders should you accept?
To determine if an order should be accepted compare the quantity of the order to the accumulated available-to-promise (ATP) inventory. If there is not sufficient ATP inventory, then the order should not be accepted.
Order number 1 (should/should not) be accepted.
Order number 2 (should/should not) be accepted.
Order number 3 (should/should not) be accepted.
Order number 4 (should/should not) be accepted.
Shown below is a partially completed MPS record for ball bearings. 1 3 4 9 10 450 350 a. Develop the MPS for ball bearings. (Enter your responses as integers. A response of "O" is equivalent to being not applicable.) Item: Ball bearings Order Policy: 500 units Lead Time: 1 week Quantity Week on Hand: 400 2 5 6 7 8 Forecast 550 250 400 500 300 350 250 250 Customer orders 300 350 250 300 250 100 100 150 (booked) Projected on-hand inventory MPS quantity 500 100 50Step by Step Solution
There are 3 Steps involved in it