Question: please solve this problem using excel. Thank you. 5-21 In a job shop operation, four jobs can be performed on any of four machines. The

please solve this problem using excel. Thank you.

please solve this problem using excel. Thank you.

5-21 In a job shop operation, four jobs can be performed on any of four machines. The hours required for each job on each machine are presented in the following table: MACHINE X 10 14 16 13 JOB A12 A15 B2 B9 12 13 15 12 9 12 12 11 14 16 18 16 The plant supervisor would like to assign jobs so that total time is minimized. Use the assignment model to find the best solution