Question: Please to answer the following Question 1 Question 2 Question 3 Question 4 For the diagram, when would B finish? For the following network diagram,
Please to answer the following
Question 1

Question 2

Question 3

Question 4

For the diagram, when would B finish? For the following network diagram, complete the table below. ES LS LF Slack What is the critical path? 1. ABCD 2. ABD 3. ACD 4. BAD 5. DCA 6. DBA What is the length of the project? A lead of 3 days on A would result in B finishing after days A lag of 6 days after A would result in B finishing after days
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts