Question: please type it Based on the current data, what date should you schedule the chemical delivery? The customer requires the tank level not to go
Based on the current data, what date should you schedule the chemical delivery? The customer requires the tank level not to go below 1000 US Gallon. Please show all your work! Date Tank Level (US Gal) 10-Sep 6500 11-Sep 6000 12-Sep 4500 13-Sep 4000 14-Sep 3000 15-Sep 2800 16-Sep 2400 17-Sep 2000
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts