Question: Please use a table or chart to complete this Product A is an end item and is made from two units of B and four

Please use a table or chart to complete this
Product A is an end item and is made from two units of B and four of C. B is made of two units of D and two of E. C is made of two units of F and two of E. A has a lead time of one week. B, C, and E have lead times of two weeks, and D and F have lead times of three weeks. b. If 120 units of A are required in Week 10. develop the MRP planninq schedule, specifvina when items are to be or re
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts