Question: Please use all the mathematical terms that are needed. And please answer the whole question . The table below shows the defects from XYZ garments

Please use all the mathematical terms that are needed. And please answer the whole question .
The table below shows the defects from XYZ garments factory. Defect type Total defects Skip stitch 2909 Loose thread 43 Misplaced embroidery 300 Needle damage 1287 Broken stitch 4509 Puckering 598 Dirty spot 44 Open seam 290 Print defect 598 Button missing 668 Label missing 1208 question: 1. Implementation of the action plan 1. Network diagram solution using deterministic times (ES, EF, LS, LF), determine critical path 2. Crashing problem (no daily budget) to show how this project can be expedited 3. Total cost needed for full expedition of the project and total days saved SOLVE THE ANSWER WITH PROPER EXPLANATIONStep by Step Solution