Question: Please use excel and show formulas. Thank you! 2. Constrained Optimization: You have identified 10 independent projects with positive NPVs. But with a budget constraint
2. Constrained Optimization: You have identified 10 independent projects with positive NPVs. But with a budget constraint of $700,000, you can only invest in a few of these projects. Show: (10 points) 2.1. which projects you will invest in 2.2. the total investment amount 2.3. the total NPV amount Project 1 2 3 4 5 6 7 Available Projects Initial Investment NPV $7,000 $600 $9,500 $2,000 $65,000 $8,000 $105,000 $9,000 $115,000 $3,000 $156,000 $6,000 $160,000 $4,000 $187,000 $15,000 $210,000 $11,000 $227,000 $8,000 9 10