Question: Please use Johnson's Rule ( > 2 M C case ) to sequence the jobs that require the same operation from M 1 - M
Please use Johnson's Rule case to sequence the jobs that require the same operation from MMMMM
a Please find the best job sequence with the lowest completion time.
b What is the "total idle time" of the best job sequence?
c What is the "idle time when the machines start" of the best job sequence?
tableJobProcessing time minsMMMMMABCD