Question: Please use PERT chart to draw the process of preparing the report. example of PERT chart : Please use the picture information below for the
Please use PERT chart to draw the process of preparing the report.
example of PERT chart :
Please use the picture information below for the topic. drew a PERT CHART
Key Beginning/ending of an activity Critical path D 1/2 week A. Get funding approval B. Remove chairs and tables C. Buy new floor tiles D. Move tables and chairs E. Remove old floor tiles F. Install new floor tiles G. Rework tables and chairs H. Return tables and chairs I. Reinstall tables and chairs B 1/2 week 6 weeks A 2 weeks H START FINISH 1 week 3 weeks 1/2 week 1 week 2 weeks FIGURE 7.12 PERT Chart motive Select industry Purpose (specific goal) Industry overview Data collection (mainly information PEST analysis from 2019 to 2021) data analysis Research results (achievement of purpose) (1920 words/page, Output report about 5-6 pages A4) 12/1 (III) Payment Seal + material origin (met ruins)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock