Question: Please use the computer to write clear step by step for calculating Liquidated damages. Question 3 (a) (8 marks) a) A construction project has reached

Please use the computer to write clear step by step for calculating Liquidated damages.
Question 3 (a) (8 marks) a) A construction project has reached Completion on 16 October 2020 and the completion was delayed by 57 days from the original signed completion date. The Liquidated Damages for the project is $95,000/ Day. Which date is the original signed completion date based on the following and calculate the total Liquidated Damages that should be paid by the Contractor? The Contractor submitted a claim of EOT for 6 days due to change in material but the Engineer decided that the event is NOT a critical event. The Contractor has submitted a claim for extension of time of 30 days for additional works that affected the critical path of the project. The Engineer granted 19 days for the Extension of Time (EOT). 6 Days of extension of time was granted to the Contractor due to Black rainstorm signalStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts