Question: Please use the following information to develop a project plan. In addition to the project activity cost there is a overhead cost of $20 /day.

Please use the following information to develop a project plan. In addition to the project activity cost there is a overhead cost of $20 /day. The client wants the project to finish by 6 days and they imposed a penalty of $50 per day after day 6 , also they will pay a bonus of $50 per day if the project finishes before day 6. What is your suggestion for the company? Please show all your network diagrams and calculations for each day with a graph showing total cost against number of days