Question: Please use the table and diagram below to answer the following question (1-12). Please help I will rate you highly! Please show your work! You
Please use the table and diagram below to answer the following question (1-12). Please help I will rate you highly! Please show your work!
You are managing the following project for installing scrubbers in a smokestack. The tasks and time estimates for the optimistic, most likely, and pessimistic times are presented in the table below:
| Time Estimate (in weeks) | |||
|---|---|---|---|
| Activity | Optimistic | Most Likely | Pessimistic |
| A | 2 | 7 | 10 |
| B | 4 | 8 | 14 |
| C | 4 | 4 | 4 |
| D | 6 | 7 | 8 |
| E | 2 | 4 | 6 |
| F | 6 | 10 | 14 |
| G | 1 | 4 | 9 |
| H | 3 | 6 | 9 |
| I | 10 | 11 | 12 |
| J | 14 | 16 | 20 |
| K | 2 | 8 | 10 |
And here is a rough diagram of what the network looks like: (If there is a discrepancy between the "Immediate Predecessor" data in the table and this diagram, use the network diagram.)

A G Start C D E K End B F H