Question: Please usee PM software : Your company is going to undertake a project to launch a new limited-quantity seasonal product. The activities involved in the
Please usee PM software: Your company is going to undertake a project to launch a new limited-quantity seasonal product. The activities involved in the project (including activity durations and dependency relationships) are shown in the table below. The project launch date is March 2, 2020. Use this information to create a project plan in Microsoft Project (MSP). Be sure to include an MSP-generated work breakdown structure (WBS) column in your project plan. Use MSPs Project Summary Task feature to compute the overall project duration. Save your MSP file under the name HW5. Submit your MSP file (.mpp) for grading in the usual way.
| Activity | Predecessor | Duration (Weeks) |
| A. Survey the market | - | 2 |
| B. Design product | - | 3 |
| C. Order raw materials | A | 3 |
| D. Receive raw materials | C | 2 |
| E. Build product prototype | D, J | 1 |
| F. Develop marketing plan | E | 2 |
| G. Launch full-scale production | E | 4 |
| H. Deliver products | F | 2 |
| J. Process regulatory approvals | B | 3 |