Question: Please utilize the information below to work the problem specified below ( it is problem 3 . 8 from the text ) . Please complete

Please utilize the information below to work the problem specified below (it is problem 3.8 from the text). Please complete the following: (1) Construct a CPM network. (2) Draw the AON network, and compute the Critical Path Utilizing the forward and backward pass. (3) Be able to articulate the critical path, as well as each activity on node time (latest start, latest finish, early start, early finish).
\table[[CODE,AC TIVITY,DESCRIPTION,TIME (IN HOURS),IMMEDIATE PREDECESSOR($)],[A,Planning,Find location; determine resource requirements,20,None],[B,Purchasing,Requisition of lumber and sand,60,Planning],[C,Excavation,Dig and grade,100,Planning],[D,Sawing,Saw lumber into appropriate sizes,30,Purchasing],[E,Placement,Position lumber in correct locations,20,Sawing, excavation],[F,Assembly,Nail lumber together,10,Placement],[G,Infill,Put sand in and under the equipment,20,Assembly],[H,Outfill,Put dirt around the equipment,10,Assembly],[1,Decoration,Put grass all over the garden, landscape, paint,30,Infill, outfill]]
What is the latest start time for D?
 Please utilize the information below to work the problem specified below

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!