Christmas Express makes wreaths in batch sizes of 12. The cutting & assembly process takes 8 minutes per wreath and the decorating process time is 10 minutes per wreath. It takes 12 minutes to move the wreaths from the cutting & assembly process to the decorating process. Compute the non-value-added lead time. 198 minutes 0216 minutes 228 minutes 210 minutes