Question: plesae 2 ) Calculate Early Start ( ES ) , Early Finish ( EF ) , Late Start ( LS ) , Late Finish (

plesae 2) Calculate Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and Total Float (TF) for each task. activity table is attached as a picture, please give answer and calculations
3) What is the total duration of the Stage 1 of this project?
4) Identify and show the Critical Path for the stage 1
Question 1B (10 marks)
One of your team members working on the Task Review and customise training material has just had a baby and would need to go on maternity leave, a suitable maternity cover will not resume earlier than a month. The project has been struggling with limited resources, hence, the delivery of this Task would be delayed by 40 working days.
Determine the impacts this would have on your schedule.
 plesae 2) Calculate Early Start (ES), Early Finish (EF), Late Start

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!