Question: plesae 2 ) Calculate Early Start ( ES ) , Early Finish ( EF ) , Late Start ( LS ) , Late Finish (
plesae Calculate Early Start ES Early Finish EF Late Start LS Late Finish LF and Total Float TF for each task. activity table is attached as a picture, please give answer and calculations
What is the total duration of the Stage of this project?
Identify and show the Critical Path for the stage
Question B marks
One of your team members working on the Task Review and customise training material has just had a baby and would need to go on maternity leave, a suitable maternity cover will not resume earlier than a month. The project has been struggling with limited resources, hence, the delivery of this Task would be delayed by working days.
Determine the impacts this would have on your schedule.